S5W-13882: Neil Findlay (Lothian)

Scottish Labour

Date lodged: 17 January 2018

To ask the Scottish Government, further to the answer to question S5T-00865 by Keith Brown on 16 January 2018 (Official Report, c. 3), what contracts (a) it, (b) its agencies and (c) the Scottish Futures Trust has or has had with Carillion, broken down by (i) the value of the contract, (ii) the date the contract was signed and (iii) the date the contract was or is expected to be completed.

Answered by: Keith Brown 31 January 2018

a) The Scottish Government does not have any contracts direct with Carillion.

b) The following table lists contracts between Carillion and SG agencies taken from the Public Contract Scotland (PCS) system. These records go back to start of PCS in 2008:

Contract Name

Contracting Authority

Award Date

End Date

Estimated Value on Completion

Bridge Maintenance; emphasis on Joints, Bearings, Parapets etc.

Transport Scotland

11-08-2004

22-10-2004

£579,107.00

Minor Road Improvements Improvement Works

Transport Scotland

02-05-2007

07-09-2007

£525,234.00

Bridge Maintenance; emphasis on Joints, Bearings, Parapets etc.

Transport Scotland

09-02-2007

20-12-2007

£515,355.00

New Regimes / Kitchen / Laundry / Energy Centre @ HMP Edinburgh

Scottish Prison Service

13-12-2005

30-06-2008

£24,000,000.00

M & E Maintenance

Scottish Children's Reporter Administration

01-03-2003

28-11-2008

£1,500,000.00

Phase 3 Edinburgh: Enabling works/Gate Complex etc.

Scottish Prison Service

15-05-2006

31-12-2008

£14,379,556.00

Safer Cell at Greenock

Scottish Prison Service

27-05-2009

04-12-2009

£14,339.00

HMP Edinburgh Phase 4 Additional Accommodation

Scottish Prison Service

09-07-2007

08-02-2010

£10,729,717.00

Demolition at Bishopbriggs

Scottish Prison Service

15-01-2008

31-07-2010

£885,000.00

 

 

 

 

 

HMYOI Polmont Phase 5 Additional Accommodation

Scottish Prison Service

12-07-2007

11-07-2011

£12,248,869.00

Phase 3 Polmont: Enabling Works/Gate Complex etc.

Scottish Prison Service

09-07-2007

08-10-2011

£39,950,207.00

New Prison - HMP Low Moss (original working title HMP Bishopbriggs)

Scottish Prison Service

29-07-2009

29-01-2012

£98,677,723.00

FM Provider

Scottish Courts and Tribunals Service

01-10-2005

31-01-2012

£56,000,000.00

NMS Building maintenance term contracts

National Museums Scotland

01-02-2009

01-02-2012

£270,850.00

HMP Shotts: Major works

Scottish Prison Service

01-10-2006

30-09-2012

£62,000,000.00

Design & Build of the new prison at Bishopbriggs.

Scottish Prison Service

29-07-2009

31-03-2015

£98,677,723.00

Centre for Health Science Facilities Management

Highlands and Islands Enterprise

06-03-2017

27-03-2017

£1,670,887.65

Enabling Works for HMP Inverclyde

Scottish Prison Service

23-12-2013

31-03-2017

£2,626,238.00

Aberdeen Western Peripheral Route

Transport Scotland

12-12-2014

Spring 2018

£533,000,000

Facilities Management Framework (Crown Commercial Services)

Registers of Scotland

01-10-2013

30-09-2018

£6,100,000

Contract for the Provision of Facilities Management Services

Scottish Children’s Reporter Administration+

06-01-2014

05-01-2019

£12,800,000++

FM for An Lochran

Highlands and Islands Enterprise

02-05-2016

01-05-2019

£797,450.00

Centre for Health Science Facilities Management

Highlands and Islands Enterprise

06-03-2017

06-03-2020

£1,670,887.65

+When this contract was initially awarded it was a collaborative mini competition between Historic Environment Scotland, National Museums of Scotland and Scottish Children’s Reporter Administration. Now only Scottish Children’s Reporter Administration receive services from this contract.

++Estimated value on completion includes historic spend from Historic Environment Scotland and National Museums of Scotland.

c) Scottish Futures Trust (SFT) does not have any contracts with Carillion.

In respect of the Non-Profit Distribution Programme (NPD) of 10 major projects, the contractual relationship is between the procuring authority and a private contracting entity. SFT holds no contractual relationships in these projects.

On one NPD project, the Aberdeen Western Peripheral Route, Carillion had a significant role as one third shareholder and construction joint venture partner with Galliford Try and Balfour Beatty. The public sector contracting entity on this project is Transport Scotland and is listed in response to b.).

Carillion is not a main construction or Facilities Management contractor on any Scotland-wide hub projects.

We cannot say definitively that no Carillion company is involved across the Scotland-wide hub programme, as specialist Carillion entities may be involved in delivering services down the supply chain which we are not aware of.