S5W-13373: Lewis Macdonald (North East Scotland)

Scottish Labour

Date lodged: 14 December 2017

To ask the Scottish Government, further to the answer to the Urgent Question regarding the Fortes Pipeline by Paul Wheelhouse on 12 December 2017 (Official Report, c.3), what impact the construction work on the Aberdeen Western Peripheral Route (AWPR) in the immediate vicinity of the Netherley area will have on the repair work on the pipeline.

Answered by: Paul Wheelhouse 23 January 2018

The repair works were successfully completed and road restrictions lifted on the 27th December 2017.

I am not aware of any reciprocal impacts on either the Forties Pipeline System repair works or the construction work for the Aberdeen Western Peripheral Route.