To ask the Scottish Government whether it will provide an update on the introduction of the class 385 trains on the Edinburgh-Glasgow via Falkirk line.

Answered by: Humza Yousaf 3 January 2018

Two class 385 trains have just concluded the required testing on the newly electrified Edinburgh-Glasgow via Falkirk route and the data from these dynamic tests will be part of a raft of documents which is submitted early in 2018 to gain approval from the ORR to operate the new fleet in passenger service. Two more class 385s are now in Scotland to help support the on-going driver training and staff familiarisation programme ahead of gradual service introduction of the new longer, faster, greener fleet in the coming months.