S5W-08815: Ross Thomson (North East Scotland)

Scottish Conservative and Unionist Party

Date lodged: 13 April 2017

To ask the Scottish Government what the (a) initial and (b) current projected total cost is of the Aberdeen Western Peripheral Route (AWPR) project.

Answered by: Keith Brown 8 May 2017

There has been no change to the cost for the AWPR/B-T project since contract award in December 2014 which is £745m in 2012 prices.