Question

To ask the Scottish Government how much of the £97.4 million of cladding remediation funding it has spent to date.


Answer

The most recently published figures show a cumulative spend of £7.141m which supports the assessment, urgent interim measures and remediation of those buildings with the pilot programme. Information on expenditure is published quarterly on gov.scot

https://www.gov.scot/publications/single-building-assessment-spending-information/