Question

To ask the Scottish Executive how long the temporary traffic arrangements at the Shawhead Interchange will be in place and what plans it has to alleviate any congestion and traffic flow problems that have arisen as a result of such arrangements.


Answer

The temporary traffic arrangements will be necessary until the upgrading is completed in December.The design of these arrangements and regular on-going consultation with Strathclyde Police, Amey Highways and North Lanarkshire Council are intended to alleviate congestion and traffic flow problems arising from the works.