To ask the Scottish Executive what the completion date is for the Airdrie to Bathgate rail link.


Answer

Following the Scottish Executive's decision to make available £500,000 for the advancement of the proposals, West Lothian Council is currently preparing the pre-qualification stage for a detailed feasibility study into the project. The study is expected to begin this summer and could be completed by April 2004. A private bill to promote the project could be introduced in 2005, with a view to re-opening the line in 2008.