Skip to main content

Language: English / GĂ idhlig

Loading…

Chamber and committees

Question reference: S1O-00410

  • Asked by: Christine Grahame, MSP for South of Scotland, Scottish National Party
  • Date lodged: 22 September 1999
  • Current status: Answered by Alasdair Morrison on 30 September 1999

Question

To ask the Scottish Executive what stage the report into the reinstatement of the Waverley Line from Galashiels to Edinburgh has reached.


Answer

The Scottish Borders Railway Feasibility Study started in April and is due to be completed in December. The consultants are currently conducting detailed economic, social and environmental analyses of a number of selected options for reinstatement.