Question
To ask the Scottish Executive what stage the report into the reinstatement of the Waverley Line from Galashiels to Edinburgh has reached.
Answer
The Scottish Borders Railway Feasibility Study started in April and is due to be completed in December. The consultants are currently conducting detailed economic, social and environmental analyses of a number of selected options for reinstatement.