Skip to main content

Language: English / GĂ idhlig

Loading…

Chamber and committees

Question reference: S5W-29800

  • Asked by: Edward Mountain, MSP for Highlands and Islands, Scottish Conservative and Unionist Party
  • Date lodged: 9 June 2020
  • Current status: Answered by Jeane Freeman on 10 July 2020

Question

To ask the Scottish Government when it was last given an update from NHS Highland regarding the development of the North of Scotland Elective Care Centre.


Answer

The National Elective Centre Programme received a report update on 2 nd June regarding the NHS Highland Elective Centre Project. This followed a discussion with the NHS Highland Elective Centre Senior Responsible Owner on 28 th May and a follow-up discussion took place on Monday 15 th June.

The National Elective Centre Programme is regularly updated on the development of the North of Scotland Elective Care Centre.

Construction is due to commence in June 2020 with a Construction Completion Date of August 2022.